Oak Street School - Modernization Project
Oak Street School – Modernization & Sound Mitigation Project
Project Scope | |
Modernization
Accessibility upgrades
Classroom finishes
Restroom renovations
Flooring replacement
Lighting replacement
Painting (interior & exterior)
Technology infrastructure upgrades
Site development (field restoration, perimeter fencing, courtyard and parking lot upgrades)
Sound Attenuation Improvements
|
|
Project Schedule | |
Construction Start: November 2019
Project Completed: July 2022
|
|
Project Budget | |
Project Cost: $19.1 million
Funding Sources: Measure GG, Los Angeles World Airports (LAWA)
|
Oak School Construction Pictures