Project Scope
New Construction:
  • New classrooms (8)
  • New administration building
  • New multi-purpose room
 
Site Development:
  • Demolition of existing CDC campus
  • Exterior lighting
  • New outdoor play areas
  • Landscaping
  • New parking & drop-off areas
Project Schedule
Design Start: Fall 2023
Design Completed: September 2024
Construction Start: July 2025
Project Completed: July 2026
Project Budget
Overall cost: $15 million
Funding Sources: Measure I, developer fees, outside contribution (Harridge Developers)