Inglewood High School - Reconstruction Project
Inglewood High School – Reconstruction Project
Project Scope | |
New Construction:
Modernization:
Site Development:
|
|
Project Schedule | |
Design start: Spring 2022
Design completed: Fall 2025
Construction Start: Summer 2025
Project Completed: December 2027
|
|
Project Budget | |
Overall cost: $232 million
Funding Sources: Measure I, developer fees, State funding (Office of Public School Construction)
|